COURSE AND NEW CLUBHOUSE NEWS

This week we received delivery of the tiles for all of the club’s locker rooms and amenities. From next week a whole new stage of contractors will be starting work on the clubhouse finishes.

Read More

COURSE AND NEW CLUBHOUSE NEWS

The builders are focusing much of their efforts on the clubhouse services, especially the Fire Protections system. This involves the completion of the hydrant pump room which also feeds the automatic fire sprinkler … Read More

COURSE AND NEW CLUBHOUSE NEWS

Yesterday morning the ramp up to the club entry and carpark was poured. This ramp requires a substantial curing period, so it is great to have this ticked off. There is also a … Read More

A new course routing was brought into play on Monday 23 April 2018, bringing into play our new 15th and 16th greens. The course routing will follow the same route that we previously played. The 2nd and 6th temporary greens have been taken out of … Read More

COURSE AND NEW CLUBHOUSE NEWS

Over the last few days trenching alongside the new clubhouse entry road has been taking place, and the trench is now complete along the whole length of the road. Stormwater pipes are being … Read More

COURSE AND NEW CLUBHOUSE NEWS

It is another busy week at the clubhouse as the time for us to commence moving approaches.

The trenching and installation of stormwater along the Weeroona Road entry is now underway. This is … Read More