Project Legacy

NEW CLUBHOUSE CONSTRUCTION

Construction of the new clubhouse

Construction of the new clubhouse began at the end of October 2016. 

EASTERN COURSE WORKS STAGE 2

Stage 2 of the Eastern side course work.

This stage involves renovations of the eastern Freshwater Park area of the course. This is the area of the old 2nd and 14th green and 3rd and 16th tee areas. This stage involved the … Read More

EASTERN COURSE WORKS STAGE 1

Stage 1 of the Eastern side course work. This stage involves the building of the new 10th and 14th greens, along with tee complexes for the 10th, 11th and 15th holes. Work on stage 1 commenced on 14 June 2017.

Read More

WESTERN COURSE WORKS STAGE 2

Stage 2 of the Western side course work.

This stage involved the construction of the new 1st, 2nd and 7th greens, along with construction of the tees for the 2nd, 3rd and 8th holes. 

WESTERN COURSE WORKS STAGE 1

Stage 1 of theWestern side course work. This stage involves the building of the new 3rd, 6th and 18th greens, along with tee complexes for the 6th and 7th holes. Work on stage 1 commenced in March 2016.

10 March 2017: Metro work site

Below is a video of the current state of the Metro work site, located on the clubs old practice fairway.

https://vimeo.com/207880012

3 March 2017: Course and Clubhouse Works

 Heavy rain has delayed much of the work on the new holes and the clubhouse site. We have, however, been able to carry on with the installation of the new irrigation pumps and lines and once this is hooked up … Read More

24 February 2017: Course Works

The third irrigation pump has arrived and been installed. To enable this to be connected we have had to completely disconnect our irrigation system for the week. Course staff are hand watering greens (from mobile water tanks) twice daily during … Read More