January, 2018 Monthly archive

COURSE AND NEW CLUBHOUSE NEWS

Work on our new clubhouse continues to progress, and each day we are a little bit closer to completion.

The main activity at the clubhouse is installing the mass of cables … Read More

COURSE AND NEW CLUBHOUSE NEWS

Clubhouse works are going full steam ahead. The building is swarming with contractors with numerous projects all being worked on concurrently.

The wall sheeting on the lower ground floor is ongoing … Read More

COURSE AND NEW CLUBHOUSE NEWS

After a break over the Christmas and New year period, work on both the clubhouse and course have ramped back up.

At the clubhouse site after further delays prior to Christmas, … Read More

Construction of the new clubhouse

Construction of the new clubhouse began at the end of October 2016. 

Stage 2 of the Eastern side course work.

This stage involves renovations of the eastern Freshwater Park area of the course. This is the area of the old 2nd and 14th green and 3rd and 16th tee areas. This stage involved the … Read More

Stage 1 of the Eastern side course work. This stage involves the building of the new 10th and 14th greens, along with tee complexes for the 10th, 11th and 15th holes. Work on stage 1 commenced on 14 June 2017.

Read More

Stage 2 of the Western side course work.

This stage involved the construction of the new 1st, 2nd and 7th greens, along with construction of the tees for the 2nd, 3rd and 8th holes. 

Stage 1 of theWestern side course work. This stage involves the building of the new 3rd, 6th and 18th greens, along with tee complexes for the 6th and 7th holes. Work on stage 1 commenced in March 2016.